Audit Report Reveals 89% of Railway Stations Lack Minimum Amenities
A recent audit highlights critical deficiencies in basic facilities at 89% of Indian railway stations, raising concerns about passenger welfare.

Audit Report Exposes Lack of Minimum Facilities at 89% of Railway Stations
Amidst government claims of improving passenger amenities at railway stations, a recent audit report has cast serious doubt on the ground reality. Investigations conducted at 512 selected non-suburban railway stations across 16 railway zones nationwide have revealed shocking facts.
According to the report, 458 stations, representing over 89 percent of the total, are struggling with one or more deficiencies in the minimum essential facilities prescribed for passengers. Only 54 stations were found to have all necessary facilities meeting minimum standards during the inspection.
This report not only points to a lack of facilities but also expresses serious concerns regarding the quality of drinking water, the condition of toilets, medical facilities, arrangements for passengers with disabilities, delays in construction work, and the utilization of allocated budgets for passenger amenities at many stations.
Significant Shortage in Basic Amenities
Essential passenger needs at railway stations include fans, clean drinking water, adequate seating arrangements, accessible toilets, platform sheds, and water coolers. However, a large number of stations were found to be lacking these facilities at the prescribed levels.
The report reveals that approximately 42 percent of the inspected stations showed a shortage or inadequacy of fans. Around 40 percent of stations had water cooler arrangements not conforming to standards. Approximately 27 percent of stations had either insufficient or absent drinking water taps, while around 22 percent recorded deficiencies in urinal facilities.
Alarmingly, this deficiency is not limited to smaller stations; many larger stations with higher revenue and passenger traffic also showed flaws in essential amenities. This situation underscores a systemic issue rather than isolated incidents.
Serious Concerns Over Drinking Water Quality
The state of drinking water at railway stations has also heightened concerns for passenger health and safety. At many locations, samples of drinking water tested positive for harmful bacteria like coliform and E. coli.
Bacterial contamination was also found in water samples taken from water coolers at some stations. Furthermore, the residual chlorine levels in the water did not meet prescribed standards at several locations. This indicates that merely ensuring water availability is insufficient; regular testing, cleaning of water coolers, and continuous monitoring of the water supply system are crucial.
Deficiencies in Medical and Disability Facilities
The condition of medical facilities was also found to be unsatisfactory. Approximately 441 stations lacked essential facilities like emergency medical rooms or recommended medical boxes. This raises questions about the provision of immediate first aid to passengers in emergencies, especially for the elderly, children, and those with serious health conditions.
Similarly, a widespread lack of facilities for passengers with disabilities was identified. At many stations, amenities such as ramps, accessible toilets, easy access to water facilities, lifts, tactile paths, and proper information systems were either incomplete or did not meet prescribed standards. This causes significant hardship for passengers requiring more assistance to navigate the station premises.
The report also indicated that even where these facilities were available, their maintenance or operation was not effective at many stations.
Delays in Construction and Misuse of Budget
The pace of construction and development work undertaken by the railways to improve passenger amenities is also under scrutiny. A review of 395 passenger facility projects from 2019-20 to 2023-24 found that approximately 59 percent of these works were not completed within the stipulated timelines.
Only 41 percent of the projects were completed on time, with many projects experiencing delays ranging from one to four years or more. Reasons cited for these delays include poor planning, issues with material availability, a shortage of skilled labor, and contractor-related problems. Additionally, questions were raised about the utilization of the allocated budget for passenger amenities. Between 2019-20 and 2023-24, 36 to 44 percent of the available budget for passenger amenities remained unspent in several years.
This situation suggests that the problem is not just a lack of funds but also flaws in the processes of planning, prioritization, project initiation, monitoring, and timely completion of projects.
Serious Deficiencies in Sanitation Systems
The sanitation system within station premises was also part of the audit. At many stations, the condition of toilets was found to be poor, with broken seats or damaged doors. In some places, the regular cleaning and maintenance of toilets were also found to be unsatisfactory.
Deficiencies related to cleanliness were also noted in waiting halls, foot overbridges, and around platforms. Stains from pan masala and chewing tobacco were visible at many locations, and in some stations, open defecation was also observed. Such conditions pose a challenge not only to passenger convenience but also to station hygiene and public health.
Situation of Major Stations in Madhya Pradesh
The condition of railway stations in Madhya Pradesh is not exempt from this grim picture. Deficiencies related to various passenger amenities were recorded at major railway hubs in the state, including Bhopal, Jabalpur, Gwalior, and Ratlam. However, Indore Railway Station was among the select 54 stations where no deficiencies were found in the prescribed minimum essential facilities during the audit. It is important to note that this assessment was based solely on the specific minimum standards examined in the audit.
Systemic Problem Demands Immediate Solution
The data revealed in the audit clearly indicates that the lack of passenger amenities at railway stations is not an isolated issue of a single station or railway zone but a widespread and systemic problem. Despite the railways having prescribed standards, budgets, and monitoring mechanisms, the absence of basic facilities at a large number of stations raises questions about the implementation system.
For the railways, which serve millions of passengers daily, the basic amenities at stations are not an additional perk but an essential part of passenger service. The timely availability of facilities like water, toilets, seating, fans, medical assistance, and ramps for passengers with disabilities is a matter of passenger dignity and safety.
The audit report presents a clear challenge to the railways. The need now is not just for the announcement of new schemes but for the time-bound completion of already planned facilities, effective utilization of budgets, and ensuring regular monitoring at every station, so that the basic needs of millions of passengers can be met.